Why operational responsibilities need to be ironed out early

Vicky McCombe

Simon Lewis

Simon Lewis and Vicky McCombe from law firm Womble Bond Dickinson look at what the second edition of the CIC BIM Protocol means for facilities management.

In our recent review of the second edition of the CIC BIM Protocol (Second Helpings) we noted references to an asset information model (AIM) which had been introduced and suggested that the implications of using the Protocol for the facilities management (FM) phase of a project needed to be worked through. 

In this article we consider how BIM will operate during the FM phase and the practical issues this raises.

Given that the application of BIM to existing assets is bound to be more extensive and consequently involve greater resource than the application of BIM to new build alone, it is important to understand the structure of the underlying PAS 1192-3 and the practical issues that arise. 

PAS 1192-3 is concerned with the availability, integrity and transfer of data and information during the operational phase of an asset’s life. It introduces the AIM which is, as the CIC Protocol points out, a maintained information model which is intended to govern the use, maintenance and operation of the asset. 

The obvious difference between the AIM and the information model that operates in the new build phase (which used to be referred to as the project information model (PIM)) is that the AIM will have to cater for a more flexible sequence of activities through the asset life cycle, dealing with a mixture of planned and unplanned events that could happen in any order between the points of asset handover and asset disposal. 

These planned and unplanned events are referred to in PAS 1192-3 as “triggers”. Either an AIM will already be in existence when a trigger occurs or a new AIM can be created in response to a trigger and at the inception of a trigger-related event.

Triggers would therefore include planned and unplanned maintenance works, refurbishment and update, variations and end of life works such as demolition, decommissioning and mothballing.

The AIM should be put in place at the beginning of the FM phase of the asset’s life cycle or when that asset is acquired by its new owner if there is not already an AIM in place.

If the asset remains in continued ownership from the new build phase through to the FM phase, paragraph 10.2.1 of PAS 1192-2 requires the constructor to create an “as built” PIM to act as the foundation for the AIM in the next phase. The AIM then develops and evolves over the course of the FM phase of the asset life cycle.

The capturing of the information necessary to go in to the AIM is likely to be over a much longer period of time than the new build phase and also requires a slightly different information structure to support the AIM.

This would include recording the organisational information requirements (OIR) of the organisation that owns the asset, being the data and information required to achieve the organisation’s objectives, as well as the asset information requirements (AIR), which is the data and information requirements of the organisation in relation to the asset itself. 

This information would be administered by the asset information manager and the data manager (who controls the reception and transfer of information).      

One of the advantages of BIM is the ability to provide accurate information about an asset. As with the PIM it is therefore vitally important that the AIM contains good quality up to date data and there needs to be a process set out in any FM contract to deal with this just as there should be in a construction contract.

Documents such as the AIR and the OIR (which are broadly the equivalent of the Employer’s Information Requirements during the construction phase) should set out this process to achieve the requirements of PAS 1192-3. Those documents should be incorporated into any FM contract along with obligations on both parties to comply with these.

A priority clause should also be included in the FM contract to deal with any inconsistencies between these documents and the others that form part of the contract.

Consideration should be given as to who will carry out the new roles of asset information manager and data manager specified in PAS 1192-3 and be responsible for assuring data and information flow to and from the AIM.

This could either be by dedicating someone in house to do this role or appointing someone externally. It may also be that the same person can undertake both functions. Again we would also suggest that those roles are identified within the FM contract along with an obligation to comply with their reasonable instructions.

Another issue which is familiar from the construction phase is ownership of the AIM and intellectual property rights within it. This should really be considered during the construction phase if ownership of the asset is not being sold or transferred at the end of its construction.

The intellectual property rights in the construction contracts will need to allow for use for the purposes of facilities management and any licences will need to include a right to grant sub-licences. Any FM contract will also need to deal with intellectual property rights and ownership of the AIM.

It is worth noting at this point that the operational phase could throw up other issues here which will need to be considered. For example, some services may be carried out by a tenant and others by the landlord.

What happens to the model after the lease ends, either by way of expiry or termination? If the asset is sold the AIM will need to go with it along with the necessary transfer of intellectual property rights. This takes BIM considerations beyond the FM contract potentially into sale and lease arrangements.

The FM contractor may want to look at whether it should be entitled to compensation or relief in the event that incorrect information in the AIM (which is not as a result of information provided by the facilities manager) results in additional costs or delays to them in the carrying out of the services.

When considering the use of BIM throughout the life cycle of an asset, progressing from PAS 1192-2 to PAS 1192-3, it is clear that the most efficient and cost-effective approach is to create the PIM whilst having the requirements of the FM phase in mind. In other words, the FM sector should be involved at the design concept stage of any project. 

In short, start with the end in mind and involve the FM team when developing the design of your project. 

The structure of PAS 1192-2 and 3 contemplate a virtuous circle where the AIR feeds into the Employer’s Information Requirements, which leads to the development of the PIM, which in turn contributes to the AIM.

Consequently, the AIM should be a product of both the EIR and the AIR. This must make sense in the context of the cost savings that can be obtained by constructing a building in such a way that it is efficient to run.

As is apparent from even this short description of the use of BIM in the FM phase, the CIC BIM Protocol would need to be substantially changed to deal with these new concepts, offices and responsibilities rather than just referring in passing to the AIM. 

It is useful that the authors of the Protocol have drawn attention to the need to consider the use of BIM at the FM stage, but we believe that it would be preferable to create a separate protocol dealing solely with the FM stage to mirror the PAS 1192 2 and 3 structure and to cater adequately for the practical and contractual issues that will inevitably arise as the use of BIM in FM becomes more widespread.   

Simon Lewis is a partner and Vicky McCombe a managing associate in the construction and engineering team at Womble Bond Dickinson

Main image: Meinzahn/Dreamstime.com

Story for BIM+? Get in touch via email: [email protected]

Comments

  1. Towards the end of the article you refer to the AIM being a product of the EIR. Which EIR? Remember that an EIR is purpose driven. There should be a seperate type and style of EIR for operational (post handover) activities i.e during construction you want to know from supply chain when boiler_02 needs maintaining, but post comstruction you want to know from your maintenance subcontractor when it was last serviced. This smaller EIR will go into that maintenance providers contract. It has to or you may loose all the data if he moved on. I see post contruction as almost identicial to the construction stage. People produce information that you need and so if you setup processes so that they can be combined into your AIM (the databases that hold the original handover data + extra data since then) then I don’t see why the same protocol can’t apply. You tell each information provider/consumer what you want and tell them how you want to use it (so to cover licence of use permits noted in the protocol) and you work as the construction teams did. The reality is, however, that although construction managers are considered poor at managing the process… I would say FM/operational teams are even worse and also need IM specialists to carry out IM role.