Projects

Case study: BIM helps deliver complex Central Dublin office renovation

Careful coordination and collaboration has transformed a brick and concrete 1970s office block in the heart of Dublin into a bright and light-filled space fit for modern businesses.

Owner MF Properties, part of Irish developer Castlepark, approached Dublin-based architectural practice Lafferty with a brief to completely refurbish and extend Scotch House to create premium office accommodation available to let.

It was the first time a private sector client had approached Lafferty with a clear BIM aspiration – MF Properties had already procured a point cloud survey of the property and prepared an IFC 3D model of the building.

Planning permission was granted in 2016 and MF Properties gave Lafferty the go-ahead in March 2017. The building is expected to be completed in early 2019.

Adding height and light

Comprising six storeys and a basement level, the original building was a concrete structure with brick facades. The project involved an extensive overhaul including the replacement of two of the facades, substituting the brick with an elegant Portland stone, enhanced with powder-coated aluminium floor-to-ceiling glazing.

The two upper floors provide penthouse accommodation with full-height, double-glazed facades, offering uninterrupted views of the river Liffey and surrounding area. External roof terraces at the penthouse levels offer attractive landscaped outside space.

The project involved an extensive overhaul including the replacement of two of the facades

According to Ronan Carroll, associate director at Lafferty, the floor-to-ceiling heights within the building were a complex challenge. As the original building was constructed with concrete, there was little opportunity to change the heights. This was of particular concern to the client, who was keen that the new space should feel both light and open.

After several investigations, Lafferty’s solution was to route the ventilation and services through the recessed profiles on the underside of the existing concrete slabs, instead of via the ceiling void, saving valuable height along the way.

Temporary steel frame

As part of the renovation, Lafferty worked with the structural engineer and steel subcontractor to construct a replacement structural frame on the two principal facades of the building. This required the construction of an additional temporary steel frame to hold up the floors until the new structural frames were put in place.

The structural and services engineers produced their model using Revit and this was transferred to Lafferty’s ArchiCAD model via IFC.

The original building was a concrete structure comprising six storeys and a basement level

In this way, the team was able to check the models for any coordination issues early on and throughout the project. During construction the steel fabrication model was provided for approval in a 3D format which greatly assisted the approval process.

In addition, Lafferty used ArchiCAD’s renovation filters extensively throughout the project, which made it much easier to immediately see the impact of alterations to the design.

BIM coordination and collaboration

Lafferty employed an external BIM consultant for the project, who undertook the clash detection between the structural, architectural and services models using Solibri. Lafferty worked on the detailed design stage until the end of July 2017. IFCs extracted from the structural and mechanical and engineering models were imported into ArchiCAD and overlaid.

Every Friday the different parties shared their respective models via IFC and every fortnight Lafferty hosted a formal BIM coordination workshop with the BIM consultant. In between, the teams shared information via screengrabs and email.

Scotch House has a prominent location in the Liffey Quays area of Dublin

Lafferty has also been heavily involved throughout the construction phase due to the complex nature of the project.

Carroll says: “There were no straight lines in the existing building, so it’s been a constant work in progress – we’ve continued to regularly update the BIM model and worked closely with the main contractor, Flynn Management, at every stage throughout the build.

“Although this project wasn’t tendered as a BIM project, we have in fact followed the BIM process informally at every stage throughout. This has proved very useful in enabling us to deliver such a complex renovation.”

Collaboration, communication and coordination have been the critical factors throughout this challenging renovation. The end result will be an elegant building that both respects and enhances its prominent location in the historic Liffey Quays area of Dublin.

www.lafferty.ie

www.graphisoft.co.uk

Story for BIM+? Get in touch via email: [email protected]

Comments

  1. Very good example of a well informed client on implementing BIM Model process and its collaboration
    between disciplines/ stakeholders.

  2. I wonder why it wasn’t tendered as a BIM project, when all the necessary work appears to have been done to allow this?

Comments are closed.

Latest articles in Projects